# Research Project Plan Template

By the end of this guide, you will be able to draft a complete research project plan for a life science project, break the work into scheduled tasks, calculate how much delay your timeline can absorb, assign roles and risks, and manage the plan once the work starts. You will also see a filled-in research project plan template example for a review project, plus worked calculations you can copy.

To follow along, you need a word processor, a spreadsheet application such as Microsoft Excel, Google Sheets, or LibreOffice Calc, and optionally a Gantt chart tool such as a project management platform or the Gantt features built into many spreadsheets. If you are responding to a funder, keep their call for proposals open in a second window, because most funding agencies specify required sections and page limits.

## What a Research Project Plan Is (and Is Not)

A research project plan is an internal working document that states what your project will do, how it will do it, who will do it, when each piece happens, and what you will do when something slips. A research proposal, by contrast, is a persuasive document written to win approval or funding before the work starts. The two share content, but the plan is the version you actually run the project with, updated as reality arrives.

The plan matters because even well-funded, experienced teams hit predictable trouble. An analysis of several convergent, co-produced coastal research projects funded through the National Science Foundation's Coastlines and People program found that teams faced epistemological, relational, temporal, and institutional challenges, and the authors' core recommendations included planning for delays, embracing flexibility, and building partnerships for the long haul [1]. A written plan is where those commitments live. Without one, "we will be flexible" becomes an excuse rather than a schedule decision.

Good research project management rests on three documents. The plan defines the work. The protocol defines the scientific method in enough detail that someone else could repeat it. The risk register defines what can go wrong and what you will do about it. This template covers all three.

## Research Project Plan Template Format: The Twelve Sections

The format below works for graduate theses, grant-funded projects, systematic reviews, and lab-based studies. Most funders and institutions expect these same sections in some order.

1. **Title and administrative block.** Short title, version number, date, project owner, and contact information.
2. **Background and rationale.** What is known, what gap you address, and why now. Keep it to one page in a working plan.
3. **Research question and objectives.** One primary question, broken into specific, measurable objectives.
4. **Project type and methods.** The design, data sources, procedures, and analysis plan.
5. **Deliverables and milestones.** Concrete outputs, each with a date.
6. **Timeline.** A task list with start and end dates, usually drawn as a Gantt chart.
7. **Roles and governance.** Who does what, who decides, and who to escalate to.
8. **Stakeholder and involvement plan.** Who outside the team shapes or uses the work.
9. **Risk register.** A table of risks, likelihoods, impacts, and responses.
10. **[Data management](/blog/guides/data-management-basics-principles-processes-and-best-practices).** Where data lives, how it is backed up, and how it will be shared.
11. **Resources and budget.** Personnel time, equipment, reagents, software, and fees.
12. **Quality checks and dissemination.** How you will verify the work and where results will appear.

The table below summarizes the sections, their purpose, and a realistic length for a working plan.

| Section | What it answers | Typical length | Owner |
|--|--|--|--|
| Title and admin block | Who owns this version? | A few lines | Project lead |
| Background and rationale | Why does this work matter? | 0.5 to 1 page | Project lead |
| Question and objectives | What exactly will we learn? | 0.5 page | Project lead |
| Methods | How will we get the answer? | 1 to 3 pages | Methods lead |
| Deliverables and milestones | What exists at the end? | 0.5 page | Project lead |
| Timeline | When does each task run? | 1 page or chart | Project lead |
| Roles and governance | Who does and decides what? | 0.5 page | Project lead |
| Stakeholder plan | Who else shapes the work? | 0.5 page | Engagement lead |
| Risk register | What could go wrong? | 1 page | Whole team |
| Data management | Where does data live? | 0.5 to 1 page | Data steward |
| Resources and budget | What does it cost in time and money? | 0.5 to 1 page | Project lead |
| Quality and dissemination | How do we check and share results? | 0.5 page | Whole team |

Save this skeleton as your starting file:

```text
# PROJECT PLAN: [Short title]
Version: 1.0 | Date: YYYY-MM-DD | Owner: [Name, email]

## 1. Background and rationale
## 2. Research question and objectives
   Primary question:
   Objectives (specific, measurable, assigned, realistic, time-bound):
## 3. Project type and methods
   Design:
   Data sources and sample:
   Procedures:
   Analysis plan:
## 4. Deliverables and milestones
   M1 (Month X):
   M2 (Month X):
## 5. Timeline
## 6. Roles and governance
## 7. Stakeholder and involvement plan
## 8. Risk register
## 9. Data management
## 10. Resources and budget
## 11. Quality checks
## 12. Dissemination
```

## Step-by-Step Walkthrough: Building Your Plan

### Step 1: Define the question and objectives

Write one primary question in a single sentence. For intervention and exposure questions, use the PICO structure: Population, Intervention or Exposure, Comparator, Outcome. For example: "In adults with type 2 diabetes (P), does structured exercise (I) compared with usual activity (C) reduce posttraumatic stress symptom scores (O)?" Then split the question into two to five objectives, each starting with a verb such as estimate, compare, characterize, or validate. Vague objectives such as "explore the topic" cannot be scheduled, and unschedulable objectives are the most common reason project plans fail.

### Step 2: Match the methods section to your project type

Different life science projects need different method sections, and your plan should borrow the structure of the closest published model. Four patterns cover most cases:

**Narrative or mechanistic reviews.** These organize the literature around concepts rather than study-by-study summaries. A recent narrative review of the glymphatic system, the brain's waste-clearance pathway, structured its coverage around regulatory mechanisms such as aquaporin-4 polarization and cerebrovascular pulsatility, then around interventions that modulate those mechanisms, then around translational challenges [2]. A review of ferroptosis in drug-induced kidney injury similarly organized by mechanism, crosstalk with other cell death pathways, and drug classes, then closed by naming applications in drug safety evaluation [3]. In your plan, list the organizing concepts and the search strategy.

**Systematic and scoping reviews.** These demand a registered, repeatable protocol. A scoping review of posttraumatic stress in diabetes registered its protocol on the Open Science Framework before starting the literature search, followed the PRISMA-ScR reporting guideline, and searched seven databases, including Web of Science, PubMed, Embase, and the Cochrane Library [4]. In your plan, name your reporting guideline, your registration date, and every database you will search.

**Quantitative syntheses.** If you will pool effect estimates, plan the pooling in advance. A network meta-analysis of exercise regimens for sleep in older adults specified in advance that two researchers would extract data independently, that study quality would be assessed in RevMan, that the network meta-analysis would run in Stata, and that treatments would be ranked with the SUCRA statistic, which expresses the probability that a treatment ranks best [5]. Your plan should name the software and the ranking or summary statistic before you see any data.

**Evidence-based implementation projects.** These translate best evidence into practice inside a clinical or laboratory setting. A project on immunosuppressant adherence in kidney transplant patients planned a baseline audit, translated 18 prioritized recommendations into 23 measurable audit criteria covering structure, process, and outcome, and then ran two implementation rounds with follow-up audits [6]. Your plan should state how many audit criteria you will define and how many implementation and audit rounds you will run.

Whichever pattern you choose, the methods section of the plan should be specific enough that a colleague could review it and predict what data you will collect, in what order, and with what tool.

### Step 3: Build the work breakdown and timeline

List every task, then arrange tasks by dependency. A task that cannot start until another finishes is dependent on it. Translate the list into a Gantt chart, which is a horizontal bar chart with one row per task and columns for time. A spreadsheet is usually enough. Put months across the top, tasks down the side, and mark the span of each task.

For the worked example used throughout this article, a nine-month scoping review, the timeline looks like this:

| Task | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 |
|--|--|--|--|--|--|--|--|--|--|
| Protocol and registration | X | X | | | | | | | |
| Literature search | | X | X | | | | | | |
| Screening | | | X | X | | | | | |
| Data extraction | | | | X | X | | | | |
| Analysis and synthesis | | | | | X | X | | | |
| Writing and internal review | | | | | | X | X | X | |
| Revisions and submission | | | | | | | | X | X |

Set a milestone at the end of each major task. A milestone is a dated, binary checkpoint, such as "protocol registered" or "screening complete," not an activity. You will notice that published teams plan milestones the same way. The transplant adherence project defined its implementation and audit rounds as distinct phases with samples counted at each audit [6], which is exactly the milestone structure you want.

### Step 4: Calculate slack and protect the critical path

The critical path is the longest chain of dependent tasks, and it fixes your end date. Slack, also called float, is the amount of time a task can slip without moving the end date. Compute durations in working days so weekends and holidays do not silently shrink your schedule. This short Python script calculates working-day durations for the plan above:

```python
from datetime import date

def working_days(start, finish):
    days, d = 0, start
    while d <= finish:
        if d.weekday() < 5:
            days += 1
        d = date.fromordinal(d.toordinal() + 1)
    return days

plan = {
    "protocol_and_registration": (date(2026, 1, 5),  date(2026, 2, 6)),
    "literature_search":         (date(2026, 2, 9),  date(2026, 3, 6)),
    "screening":                 (date(2026, 3, 9),  date(2026, 4, 17)),
    "data_extraction":           (date(2026, 4, 20), date(2026, 6, 12)),
    "analysis":                  (date(2026, 6, 15), date(2026, 8, 14)),
    "writing_and_review":        (date(2026, 8, 17), date(2026, 10, 30)),
}

for task, (s, f) in plan.items():
    print(f"{task:28s} {working_days(s, f):3d} working days")
```

The expected output looks like this:

```text
protocol_and_registration      25 working days
literature_search              20 working days
screening                      30 working days
data_extraction                40 working days
analysis                       45 working days
writing_and_review             55 working days
```

Now check float by hand. Suppose your thesis or journal requires the manuscript on December 11 and writing plus revisions needs 55 working days. Counting backward, writing must start by about October 5. If your plan starts writing on October 19, you have negative float of roughly two weeks, which means a delay somewhere earlier in the chain will cascade straight to the deadline. Fix it now by overlapping tasks, for example by drafting the methods section during the screening phase, rather than discovering the problem in October.

Co-produced and collaborative projects need extra slack on purpose. The NSF Coastal Lines and People project teams explicitly recommended embracing the expanded timeline that co-production requires and planning for delays rather than treating them as surprises [1]. If your project involves external partners, add buffer time to every task that depends on their review or input.

### Step 5: Write the risk register

For each risk, record four things: a description, a likelihood rating (high, medium, or low), an impact rating, and a response you will actually take. Typical life science entries include:

- **Key personnel loss.** Response: document all procedures so a replacement can take over within two weeks.
- **Database access lapses or search yields too few records.** Response: expand to supplementary databases and gray literature, or adjust the review scope.
- **Reagent lot fails quality control.** Response: identify a second supplier during planning, not during the crisis.
- **Partner organization delays feedback.** Response: build review buffers into the Gantt chart and agree on response deadlines in writing.
- **Data loss.** Response: automated backup to two locations, tested monthly.

Rate risks honestly. A risk register full of low-likelihood, low-impact entries is a document, not a tool.

### Step 6: Assign roles and governance

For a small project, assign each task one named owner. For a team, a RACI chart clarifies who is Responsible for doing the task, Accountable for its outcome, Consulted before decisions, and Informed after them. Also name a decision path: when two co-investigators disagree about an analysis choice, who decides, and how quickly?

Large or cross-disciplinary projects benefit from a specific role the co-production literature calls a boundary spanner, a person who moves between groups and translates between them. Teams in the NSF program recommended incorporating boundary spanners and using inclusive communication practices so that community partners, clinicians, and basic scientists could build shared understanding [1]. If your project spans disciplines or institutions, write this role into the plan by name.

### Step 7: Plan stakeholder and public involvement

If patients, community members, or practitioners will shape your research, treat involvement as a planned workstream, not goodwill. The DIADEME group, a patient and public involvement initiative within a French comprehensive cancer center, structured its involvement through three written instruments: a mission statement, an engagement charter, and an annual action plan, and it recruited five patients and five citizens into a standing resource group that met across nine monthly sessions and contributed to concrete changes such as revising a colorectal cancer prevention study [7]. A plan-level version of this looks like:

```text
## 7. Stakeholder and involvement plan
Involvement objective: patients and caregivers shape study
  materials, interpretation, and dissemination.
Recruitment: through patient associations and partner networks.
Governance: engagement charter and annual action plan, agreed
  at the first two meetings.
Cadence: monthly advisory meetings, minutes circulated within
  one week.
Evaluation: structured feedback collected each meeting, plus an
  end-of-year evaluation against the charter.
Compensation and support: [state what applies at your institution].
```

### Step 8: Cover data, budget, quality, and dissemination

Data management. State where raw data will be stored, who can access it, the backup schedule, file naming and versioning conventions, retention duration, and whether data will be deposited in a public repository at the end. For human data, note the privacy plan and the approval you need from your institutional review board or ethics committee.

Budget. List personnel effort in percent or hours per month, consumables and reagents with quantities, equipment, software licenses, publication fees, and travel. Every number should trace to a quote, a published price list, or your institution's rate schedule. Never estimate reagent costs from memory.

Quality checks. Name them in advance: co-int screening of a sample of records by two reviewers, independent data extraction, a pilot run of the full pipeline on a small subset, and version-controlled analysis code.

Dissemination. List target journals or conferences, plain-language outputs for participants or community partners, and any commitments you made to funders or collaborators.

## Research Project Plan Template Example: A Filled-In Plan

Here is the front half of the plan for the hypothetical nine-month scoping review used above, filled in as a model:

```text
# PROJECT PLAN: Scoping review of exercise programs and
  psychological outcomes in adults with chronic disease
Version: 1.2 | Date: 2026-01-05 | Owner: A. Rivera, a.rivera@example.edu

## 1. Background and rationale
Psychological distress is common in chronic disease, and exercise
is widely recommended, but the range of published intervention
types makes single-study comparisons unreliable. A scoping review
will map what has been measured and how.

## 2. Research question and objectives
Primary question: What intervention types, outcome measures, and
assessment instruments have been used to study structured exercise
and psychological outcomes in adults with chronic disease?
O1. Characterize intervention types reported since 2010.
O2. Catalog outcome measures and instruments used.
O3. Identify gaps where standardized measurement is absent.

## 3. Project type and methods
Design: scoping review following the PRISMA-ScR reporting guideline.
Protocol: registered on the Open Science Framework before any
  literature search, on or before 2026-02-06.
Data sources: PubMed, Embase, Web of Science, Cochrane Library,
  plus two regional databases per the protocol.
Screening: title and abstract, then full text, by two reviewers,
  with disagreements resolved by discussion.
Extraction: a piloted charting form covering population,
  intervention, comparator, outcome, instrument, and design.

## 4. Deliverables and milestones
M1 (Month 2): protocol registered.
M2 (Month 3): search strings finalized, records exported.
M3 (Month 5): screening complete, included studies logged.
M4 (Month 7): extraction complete.
M5 (Month 9): manuscript submitted.
```

Note what the plan does not contain. It does not promise effect estimates, because a scoping review maps the evidence rather than pooling it. Matching the promises in your plan to what your design can actually deliver is a core planning skill.

## Adapting the Template to Your Project Type

![Side-by-side comparison of review, synthesis, implementation and co-produced projects showing heaviest sections and the habit to adopt.](/article-images/illustrations/research-project-plan-template-project-type-emphasis.webp)

The twelve sections stay constant. What changes is emphasis, as summarized below.

| Project type | Heaviest sections | Planning habit to adopt |
|--|--|--|
| Narrative or mechanistic review [2] [3] | Methods, background | Define organizing concepts and scope boundaries early |
| Systematic or scoping review [4] | Methods, quality checks, timeline | Register the protocol before searching, follow a reporting guideline |
| Network meta-analysis [5] | Methods, data management | Pre-specify software, independent double extraction, ranking statistics |
| Implementation or audit project [6] | Milestones, quality checks, roles | Define measurable audit criteria and a fixed number of audit rounds |
| Co-produced or community research [1] | Timeline, stakeholder plan, risk register | Add generous buffers, plan for delays, sustain partnerships long term |
| Laboratory or wet-lab study | Methods, budget, risk register | Sequence reagent orders and equipment time against the Gantt chart |

## Research Project Management After Approval

A plan is only as good as its upkeep. Once the project starts, run it on a rhythm.

**Weekly.** A 30-minute check-in per task owner: what moved, what is blocked, what is next. Update the Gantt chart in the same meeting so the plan stays the single source of truth.

**Monthly.** Compare actual progress against milestones. The transplant adherence project succeeded in part because audits were scheduled at fixed intervals with defined sample sizes rather than left to chance [6]. Apply the same logic to any recurring check, whether it is an audit, a code review, or a partner meeting.

**Quarterly.** Revisit the risk register and the stakeholder plan. Review the risk register top to bottom and retire risks that have passed. If your project involves patients or community members, evaluate the involvement itself against a written framework rather than impressions, as the DIADEME group did using a structured evaluation tool and qualitative feedback [7].

**When delays hit.** Move tasks, do not silently absorb them. The NSF co-production teams found that acknowledging the expanded timeline, planning for delays, and staying flexible were what kept partnerships intact [1]. A plan that cannot change is a plan that gets abandoned.

**Version control for documents.** Use date-stamped filenames such as `plan_v2026-03-02.docx` stored in one shared location, or a version control system if your team uses one. Circulating edited copies by email is how plans die.

## Common Mistakes and Limitations

- **Confusing the proposal with the plan.** A proposal persuades. A plan schedules. If your document has no task dates, no named owners, and no risk register, it is still a proposal.
- **Tasks with no owner.** "The team will screen the records" means nobody screens the records. Every task gets one name.
- **Timelines without buffer.** If every task sits end to end with zero slack, the first delay moves your end date. Add explicit buffer before the final deadline, and more if the work is collaborative [1].
- **Milestones phrased as activities.** "Work on analysis" is not a milestone. "Analysis complete, results table reviewed by both investigators, dated" is.
- **Methods written after data collection starts.** Registering a review protocol after the search has begun destroys the transparency that registration exists to provide [4]. Fix the protocol date before the first database query.
- **Involvement added as an afterthought.** Recruiting patients or community partners halfway through yields token input. The DIADEME experience shows that a standing group with a charter, an action plan, and regular meetings produces concrete revisions to research [7].
- **Budget items guessed.** Reagent, sequencing, and publication costs change often. Get current quotes for every line.
- **Overloaded spreadsheets.** A Gantt chart with 80 rows is unreadable. Keep the chart at 15 to 25 summary tasks and keep detail in a separate task list.
- **Ignoring the collaboration overhead.** Cross-disciplinary and community-engaged projects take longer than single-lab work, and treating them as if they do not is a documented cause of friction [1].
- **One plan, never updated.** An outdated plan is worse than none, because people stop trusting it. A five-minute weekly update is the minimum standard.

One limitation to state plainly: no template guarantees scientific success. Individual projects face specific biological, ethical, and logistical constraints that only the project team and, where relevant, an experienced mentor or institutional committee can judge. Use the template to organize those judgments, not to replace them.

## How to Check Your Finished Plan

Run through this list before you circulate the plan to an advisor, committee, or funder.

1. Every objective traces to at least one task, and every task traces to at least one objective.
2. Every task has an owner and dates in real calendar format, not text like "TBD" or "spring."
3. The critical path is identified, and float on noncritical tasks has been calculated.
4. There is buffer before every external deadline.
5. Each risk has a specific response with a named trigger, for example "if fewer than 500 records are retrieved, expand to two additional databases."
6. The methods section matches a recognized design and, for reviews, a named reporting guideline.
7. The budget matches current quotes or published rates.
8. The data management section names storage locations, backup frequency, and a repository.
9. Involvement of patients, partners, or communities, if any, has a charter, a cadence, and an evaluation method.
10. The plan has a version number and a date, and everyone who edits it knows where the current version lives.

A quick spreadsheet check catches the most common data errors. If your date formulas return `#VALUE!`, a cell contains text instead of a real date. If deleting a row produces `#REF!`, formulas referenced that row, so undo the deletion or convert the range to an Excel Table with structured references. If Excel displays a circular reference warning, an end-date formula is feeding back into its own inputs, usually a start date computed from a duration that itself depends on the end date. Break the loop by computing one of the two values as a plain constant.

## Frequently Asked Questions

### What is a research project plan template?

It is a prestructured document with the standard sections of a research plan, including background, objectives, methods, timeline, roles, risks, budget, and dissemination, that you fill in for your specific project. This article provides a twelve-section version you can copy directly.

### How is a research project plan different from a research proposal?

A proposal is written before approval to argue that the work should happen, while the plan is the working document that schedules and manages the approved work. They share content, but the plan adds task owners, dates, slack calculations, and a risk register.

### How long should a research project plan be?

A working plan for a graduate or small funded project runs about 5 to 10 pages, with longer plans justified by team size and funder requirements. Length matters less than completeness of the timeline, roles, and risk sections.

### Where can I find a free research project plan template?

Many universities, funders, and open science organizations publish free templates, and the skeleton in this article is free to copy. Always check whether your funder or institution mandates a specific format before adopting a generic one.

### What is the standard format for a research project plan?

The most widely accepted format contains an administrative block, background, question and objectives, methods, deliverables and milestones, timeline, roles, stakeholder involvement, risks, data management, budget, and dissemination plans. Funders may reorder or rename these sections but expect the same content.

### How much buffer time should I build into my research timeline?

A common starting point is 15 to 25 percent slack on collaborative or co-produced projects, because documented experience shows these timelines expand beyond initial estimates. Keep the buffer visible in the Gantt chart rather than hidden inside task durations.

### How do I include patient and public involvement in my plan?

Write it as a workstream with its own objectives, recruitment channel, governance documents such as a charter, meeting cadence, and an evaluation method. Standing groups that meet on a regular schedule produce more concrete contributions than one-off consultations.

### Can I use this template for a systematic review or meta-analysis?

Yes, and you should add protocol registration, a named reporting guideline such as PRISMA-ScR for scoping reviews, every database to be searched, double screening and extraction, and the analysis software. The filled-in example in this article shows the review version of the template.

<script type="application/ld+json">
{
  "@context": "https://schema.org",
  "@type": "FAQPage",
  "mainEntity": [
    {
      "@type": "Question",
      "name": "What is a research project plan template?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "It is a prestructured document with the standard sections of a research plan, including background, objectives, methods, timeline, roles, risks, budget, and dissemination, that you fill in for your specific project. This article provides a twelve-section version you can copy directly."
      }
    },
    {
      "@type": "Question",
      "name": "How is a research project plan different from a research proposal?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "A proposal is written before approval to argue that the work should happen, while the plan is the working document that schedules and manages the approved work. They share content, but the plan adds task owners, dates, slack calculations, and a risk register."
      }
    },
    {
      "@type": "Question",
      "name": "How long should a research project plan be?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "A working plan for a graduate or small funded project runs about 5 to 10 pages, with longer plans justified by team size and funder requirements. Length matters less than completeness of the timeline, roles, and risk sections."
      }
    },
    {
      "@type": "Question",
      "name": "Where can I find a free research project plan template?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "Many universities, funders, and open science organizations publish free templates, and the skeleton in this article is free to copy. Always check whether your funder or institution mandates a specific format before adopting a generic one."
      }
    },
    {
      "@type": "Question",
      "name": "What is the standard format for a research project plan?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "The most widely accepted format contains an administrative block, background, question and objectives, methods, deliverables and milestones, timeline, roles, stakeholder involvement, risks, data management, budget, and dissemination plans. Funders may reorder or rename these sections but expect the same content."
      }
    },
    {
      "@type": "Question",
      "name": "How much buffer time should I build into my research timeline?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "A common starting point is 15 to 25 percent slack on collaborative or co-produced projects, because documented experience shows these timelines expand beyond initial estimates. Keep the buffer visible in the Gantt chart rather than hidden inside task durations."
      }
    },
    {
      "@type": "Question",
      "name": "How do I include patient and public involvement in my plan?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "Write it as a workstream with its own objectives, recruitment channel, governance documents such as a charter, meeting cadence, and an evaluation method. Standing groups that meet on a regular schedule produce more concrete contributions than one-off consultations."
      }
    },
    {
      "@type": "Question",
      "name": "Can I use this template for a systematic review or meta-analysis?",
      "acceptedAnswer": {
        "@type": "Answer",
        "text": "Yes, and you should add protocol registration, a named reporting guideline such as PRISMA-ScR for scoping reviews, every database to be searched, double screening and extraction, and the analysis software. The filled-in example in this article shows the review version of the template."
      }
    }
  ]
}
</script>

## Sources

1. [Navigating the practice of co-produced convergence research: Lessons from projects funded by NSF's Coastlines and People (CoPe) program.](https://pubmed.ncbi.nlm.nih.gov/43011587/)
2. [The Glymphatic System: From Basic Research Advances to Non-Invasive Brain Stimulation Applications-A Narrative Review.](https://pubmed.ncbi.nlm.nih.gov/42979929/)
3. [Research progress on ferroptosis in drug-induced kidney injury.](https://pubmed.ncbi.nlm.nih.gov/43007468/)
4. [Reported Prevalence and Associated Factors of PTSD and Posttraumatic Stress Symptoms Among Individuals With Diabetes: A Scoping Review.](https://pubmed.ncbi.nlm.nih.gov/43004151/)
5. [What exercise regimen is most effective for improving sleep quality in older adults? a systematic review and network meta-analysis.](https://pubmed.ncbi.nlm.nih.gov/42970245/)
6. [Improving immunosuppressant medication compliance management in adult kidney transplant patients: an evidence-based practice project.](https://pubmed.ncbi.nlm.nih.gov/42972352/)
7. [Patient and public involvement in a cancer prevention research department: lessons learned from the DIADEME group.](https://pubmed.ncbi.nlm.nih.gov/43004484/)