Budgeting for Farrowing and Nursery Barn Renovations

By Dr. Zubair Khalid, DVM, MS, PhD ·

Budgeting for Farrowing and Nursery Barn Renovations

Key Takeaways

  • A comprehensive farrowing barn renovation budget should be initiated at least 12 months prior to construction, with a contingency fund of 10-15% allocated for unforeseen structural issues, as renovations typically cost 40-70% of new construction.
  • Prioritize structural integrity, flooring, drainage, ventilation, and piglet survival features over cosmetic upgrades, as failing floors and inadequate air quality directly impact animal health and economic outcomes.
  • Thoroughly assess existing facility systems, including floors, walls, ventilation, plumbing, electrical, insulation, and biosecurity, ranking issues by urgency to define the renovation's scope and budget.
  • Clearly defined, measurable renovation goals, such as reducing preweaning mortality by a specific percentage or cutting heating costs, are crucial for guiding project decisions and evaluating success.
  • Obtain at least three detailed contractor bids based on a written scope of work, verifying references and credentials, and prioritize experienced contractors specializing in swine facilities to ensure quality and avoid costly rework.
  • Schedule renovations around production cycles to minimize disruption and lost revenue, and maintain meticulous records of all expenses for tax purposes and to inform future capital investment decisions.

Renovating a farrowing or nursery barn is one of the largest capital investments a swine operation can make. This guide walks you through the full planning process, from assessing your current facility and setting a realistic farrowing barn renovation budget to choosing materials, scheduling construction around your production cycle, and tracking costs over time. It is written for independent producers, farm managers, and family operations that want to make sound financial decisions without overbuilding or underfunding critical improvements. You will find practical steps for estimating nursery barn upgrade costs, comparing renovation versus new construction, and working with contractors, lenders, and your local extension office.

At a Glance

  • Start your farrowing facility improvement budget at least 12 months before you plan to begin construction.
  • A complete farrowing barn renovation typically costs 40 to 70 percent of what a new barn would cost, depending on the age of the structure and the scope of work.
  • Prioritize changes that improve piglet survival, sow comfort, and worker safety before cosmetic upgrades.
  • Budget 10 to 15 percent of the total project cost as a contingency fund for unexpected structural issues.
  • Plan renovations around your farrowing schedule so you do not disrupt the flow of sows and litters.
  • Get at least three contractor bids and check references before signing any agreement.
  • Keep detailed records of every expense, because these numbers will guide your next round of improvements.
  • Contact your state extension swine specialist or a veterinarian before finalizing plans that affect ventilation, biosecurity, or animal flow.

Why Renovate a Farrowing or Nursery Barn

The decision to renovate usually comes from one of several pressures. Old buildings may have failing floors, corroded gating, or ventilation systems that cannot keep up with modern stocking densities. Some producers renovate because they want to move from individual sow stalls to group housing or free farrowing systems. Others need to expand capacity without the cost of a new building. Disease pressure can also drive renovation, especially when older facilities are difficult to clean and disinfect between groups.

Understanding the reason behind your renovation matters because it sets the scope and the budget. A renovation driven by piglet survival rates will focus on different areas than one driven by labor efficiency. Write down the top three problems you want the renovation to solve. Keep that list visible during planning so you do not spend money on features that do not address your core needs.

The age of your barn is a major factor in the cost calculation. A barn from the 1980s or 1990s may need new electrical systems, insulation upgrades, and structural repairs that a barn from the 2000s does not. Older barns often have smaller dimensions that limit modern crate sizes or pen configurations. Measure everything before you start pricing materials. A barn that is 2 feet narrower than modern standards may not be worth renovating if you need to fit new equipment.

Assessing Your Current Facility

Before you can build a farrowing barn renovation budget, you need a complete picture of what you are working with. Walk through the barn with a notebook and document every system. Take photos of problem areas. Measure ceiling heights, wall lengths, alley widths, and door openings. Note the location of load-bearing posts, because these will limit where you can move walls or install new equipment.

Evaluate the following systems in order of importance:

Floors and drainage. Check for cracked concrete, spalled surfaces, and areas where urine or water pools. Floors that do not drain properly will undermine piglet health no matter how much you spend on other improvements. Look for smooth spots that could cause sows to slip. Measure the slope of the floor to confirm it moves liquid toward drains.

Walls and partitions. Inspect the condition of solid walls, paneling, and gating. Look for rot, rust, and damage from power washing. Check whether existing partitions are compatible with the crate or pen system you want to install.

Ventilation and air quality. Examine fans, inlets, controllers, and heating systems. Note the age of each component and its condition. Test whether the controller actually maintains the temperature you set. Check for dead air spaces where piglets might get chilled. Measure static pressure if you have the equipment.

Plumbing and drinking water. Trace the water lines and check for leaks. Test water flow at every nipple drinker. Look at the condition of the water heater and any medication delivery systems. Old galvanized pipes may be corroded and restricting flow.

Electrical and lighting. Inspect the service panel, wiring, outlets, and lighting fixtures. Look for exposed wires, outdated breaker panels, and fixtures that cannot handle moisture. Poor lighting makes it harder to spot sick piglets and creates safety hazards for workers.

Insulation and vapor barriers. Check the condition of insulation in walls and ceilings. Look for sagging, moisture damage, and areas where rodents have made nests. Poor insulation drives up heating costs and makes temperature control nearly impossible.

Feed and material handling. Assess the condition of feed lines, bins, and any automated feeding systems. Consider whether your renovation will require moving or replacing these systems.

Biosecurity and cleaning. Look at how easy it is to clean and disinfect the space. Smooth, sealed surfaces are easier to sanitize than porous ones. Check for cracks and crevices where organic material can hide.

Once you have documented the condition of every system, rank each item by urgency. Some problems are safety hazards that need immediate attention. Others are inefficiencies that you can address during the renovation. A few may be cosmetic and can wait.

Setting Your Renovation Goals

Clear goals turn a renovation from a vague wish into a concrete project with measurable outcomes. Write goals that are specific, time-bound, and tied to production metrics. Here are examples of well-formed goals:

  • Reduce preweaning mortality from 15 percent to 10 percent within 12 months of the renovation.
  • Cut heating costs by 20 percent through improved insulation and ventilation control.
  • Increase nursery throughput by 15 percent by adding 50 additional pen spaces.
  • Reduce labor time for cleaning between groups by 25 percent through better flooring and drainage.

Avoid goals like "improve the barn" or "modernize the facility." These do not tell you what to build or how to measure success.

Share your goals with your veterinarian, extension agent, and any contractors you consult. They may have suggestions for achieving the same outcomes at lower cost. They can also warn you if a goal is unrealistic given the constraints of your building.

Understanding the Costs of a Farrowing Barn Renovation

A farrowing barn renovation budget has several major cost categories. Understanding each one helps you compare bids and avoid surprises.

Structural repairs. This includes foundation work, wall replacement, roof repair, and floor resurfacing. These are often the most expensive line items because they involve heavy materials and skilled labor. If your building has serious structural issues, address them before spending money on equipment.

Mechanical systems. Ventilation fans, heaters, controllers, and electrical upgrades fall into this category. These systems are critical for piglet survival and sow comfort. They also represent a large share of the total budget.

Farrowing equipment. Crates, pens, flooring, feeders, and drinkers make up the equipment portion of the budget. Prices vary widely depending on whether you buy new or used and whether you choose basic or premium models.

Plumbing and water systems. New water lines, drinkers, and heating systems for water can be a significant cost, especially in older buildings where the existing plumbing is inadequate.

Insulation and climate control. Upgrading insulation, sealing air leaks, and installing better ventilation controls can reduce operating costs for years. These improvements often pay for themselves through lower energy bills.

Labor and installation. Contractor labor is a major cost, and it can vary significantly between regions and between contractors. Be sure to compare bids that include the same scope of work.

Permits and inspections. Depending on your location, you may need building permits, environmental permits, or inspections. Check with your local planning office early in the process.

Contingency fund. Set aside 10 to 15 percent of the total project cost for unexpected issues. Old buildings almost always reveal problems once you start opening walls and floors.

Lost production during construction. If you have to empty the barn during renovation, you lose the revenue from the pigs that would have been raised there. Calculate this cost and include it in your budget.

Estimating Nursery Barn Upgrade Costs

Nursery barn upgrades tend to cost less per square foot than farrowing barn renovations because the equipment is simpler. However, the same principles apply. Start with a thorough assessment, then price out each system.

The main cost areas for a nursery are flooring, pens or partitions, ventilation, heating, and feeding systems. Plastic-coated expanded metal flooring is common in nurseries because it is easy to clean and comfortable for piglets. The condition of your existing flooring will be a major factor in the total cost.

Ventilation is often the biggest challenge in nurseries because young pigs need warm, draft-free air with good air quality. If your current ventilation system struggles to maintain temperature, consider upgrading the controller, adding variable-speed fans, or improving inlet placement.

Heating costs are another major consideration. Nurseries need to maintain temperatures around 85 to 90 degrees Fahrenheit for newly weaned pigs. Poor insulation and drafty construction will drive up energy bills. Adding insulation and sealing air leaks can reduce heating costs substantially.

As with farrowing barns, get multiple bids and include a contingency fund. Nursery renovations can often be completed more quickly than farrowing barn renovations because the building layout is simpler, but do not underestimate the complexity of the mechanical systems.

Comparing Renovation Versus New Construction

One of the most important decisions you will make is whether to renovate or build new. This decision should be based on numbers, not sentiment. A complete renovation can cost 40 to 70 percent of what a new barn would cost, but the result is still an older building with some limitations.

Here are the factors to weigh:

Age and condition of the structure. If the building has serious structural problems, such as failing walls, a sagging roof, or a cracked foundation, the cost of repairs may approach the cost of new construction. In that case, building new may be the better investment.

Layout and dimensions. Modern farrowing crates and nursery pens are designed for specific building dimensions. If your building is too narrow, too short, or has posts in awkward locations, you may not be able to use modern equipment efficiently.

Insulation and energy efficiency. Older buildings are often poorly insulated, which means higher heating and cooling costs for the life of the building. New construction can be built to modern energy standards from the start.

Biosecurity. A new building can be designed with biosecurity in mind, including better cleaning protocols and animal flow. Older buildings may have design limitations that make biosecurity harder to maintain.

Permits and zoning. In some areas, renovating an existing building is easier than getting permits for new construction. Check with your local planning office before making a decision.

Timeline. Renovations can sometimes be completed faster than new construction, especially if the building shell is sound. However, unexpected problems can also delay renovations.

Resale value. A new building will generally have a higher resale value than a renovated older building. If you might sell the operation in the future, factor this into your decision.

Create a spreadsheet comparing the total cost of renovation versus new construction, including the cost of lost production during each option. Use realistic estimates for both. If the numbers are close, the new building is usually the better long-term investment.

Step-by-Step Guide to Planning Your Renovation

Follow these steps in order to keep your project on track and your budget under control.

Step 1: Define the scope of work. Write a detailed description of everything you want done, from structural repairs to equipment installation. The more specific you are, the easier it will be to get accurate bids and avoid misunderstandings.

Step 2: Set a realistic budget. Use the cost categories listed earlier to estimate the total project cost. Add a 10 to 15 percent contingency. If the total makes you uncomfortable, look for ways to reduce the scope, not the quality of the materials.

Step 3: Consult with professionals. Talk to your veterinarian about any changes that affect animal health. Talk to your extension swine specialist about design recommendations and potential pitfalls. Talk to a structural engineer if you are making major changes to the building.

Step 4: Get multiple bids. Ask at least three contractors to bid on the project. Give each one the same written scope of work so you can compare bids fairly. Ask for references and follow up with them.

Step 5: Check permits and regulations. Contact your local planning office to find out what permits you need. Also check with your state environmental agency about manure management and water discharge requirements.

Step 6: Plan the construction schedule. Work with your contractor to schedule the renovation during a time when the barn can be emptied. This may mean planning around your farrowing schedule or arranging to move animals to another facility temporarily.

Step 7: Prepare the site. Clear the barn of all animals, feed, and equipment. Clean the space thoroughly before construction begins. This makes the contractor's job easier and reduces the risk of introducing disease.

Step 8: Monitor construction closely. Visit the site regularly during construction. Take photos to document progress. Address any issues immediately rather than waiting until the end of the project.

Step 9: Inspect the finished work. Walk through the barn with the contractor and check every item on your scope of work. Test all systems, including ventilation, heating, and plumbing. Do not make the final payment until you are satisfied with the work.

Step 10: Track results. After the barn is back in production, compare your production metrics to your goals. This will tell you whether the renovation achieved what you wanted.

Common Mistakes to Avoid

Producers make several predictable mistakes when planning barn renovations. Knowing these in advance can save you time, money, and frustration.

Underestimating the total cost. Most renovations cost more than the initial estimate. The contingency fund exists for this reason. Do not treat it as optional.

Focusing on equipment before structure. New crates and feeders look great, but they will not perform well if the floors are failing or the ventilation is inadequate. Fix the building first.

Ignoring ventilation and air quality. Temperature control and air quality are the most important factors in piglet survival and growth. Do not cut corners on ventilation systems.

Skipping professional advice. A veterinarian or extension agent can identify problems you might miss. Their advice is usually free or low cost compared to the price of a mistake.

Choosing the cheapest bid without checking references. The lowest bid is not always the best value. A contractor who does poor work will cost you more in the long run.

Not planning for the disruption. Renovating a barn while it is in use is difficult and risky. Plan to empty the barn if possible.

Forgetting about biosecurity. Construction crews can bring disease onto your farm. Establish clear biosecurity protocols before work begins.

Not documenting the process. Take photos, keep receipts, and track all expenses. This documentation is valuable for tax purposes and for planning future projects.

Making decisions based on emotion. It is easy to fall in love with a feature that looks impressive but does not improve production. Stick to your goals and your budget.

Rushing the project. A rushed renovation leads to mistakes and rework. Give yourself enough time to do the job properly.

Decision Thresholds for Major Renovations

Some renovations are clearly worthwhile, while others are questionable. Use these thresholds as a rough guide, but always do your own math.

Replace versus repair flooring. If more than 30 percent of the flooring needs repair, replacement is usually the better option. Patching old flooring can be more expensive than installing new flooring over the long term.

Upgrade versus replace ventilation. If your ventilation system is more than 15 years old and requires frequent repairs, replacement is likely more cost-effective than ongoing maintenance. New controllers and fans are more energy-efficient and more reliable.

Repair versus replace the building shell. If structural repairs exceed 50 percent of the cost of a new building, build new. This threshold is based on the principle that a renovated building will never be as good as a new one.

Add insulation versus accept energy costs. If your heating bills are more than 20 percent higher than comparable operations with modern insulation, the investment in insulation will likely pay for itself within five to seven years.

Expand existing barn versus build new. If you need more than 30 percent additional capacity, building new is often a better investment than trying to expand an existing building. The layout of an expansion is rarely as efficient as a purpose-built facility.

Financing Your Renovation

Most producers do not pay for a renovation out of pocket. Understanding your financing options helps you plan the project and manage cash flow.

Operating loan. A short-term operating loan can cover the cost of the renovation and be repaid as the improved facility generates additional income. This works well for smaller projects with a quick payback.

Equipment loan. If a large portion of the cost is equipment, an equipment loan may offer favorable terms. The equipment itself serves as collateral.

Real estate loan. For major renovations that add significant value to the property, a real estate loan may be appropriate. These loans have longer terms and lower interest rates.

Farm Service Agency loans. The USDA Farm Service Agency offers loans for farm improvements, including building renovations. Check with your local FSA office for current programs and eligibility requirements.

Lease or rent-to-own equipment. Some equipment dealers offer leasing options that reduce the upfront cost. Compare the total cost of leasing versus buying.

Grants and cost-share programs. Some states offer grants or cost-share programs for farm improvements, especially those that improve environmental performance or animal welfare. Check with your state department of agriculture and your extension office.

Before applying for financing, prepare a clear business plan that shows how the renovation will improve your bottom line. Lenders want to see projected income statements and a realistic payback period.

Working with Contractors

The quality of your renovation depends heavily on the contractor you choose. Take time to find the right one.

Get recommendations. Ask other producers, your veterinarian, and your extension agent for names of contractors who have done good work on swine facilities.

Check credentials. Verify that the contractor is licensed and insured. Ask for proof of insurance and check that it is current.

Review past work. Ask for references and call them. If possible, visit a farm where the contractor has completed similar work.

Get everything in writing. The contract should include the full scope of work, a timeline, a payment schedule, and a process for handling changes.

Understand the payment schedule. Avoid paying a large portion of the total cost upfront. A typical schedule might be 20 percent at the start, 50 percent at the midpoint, and 30 percent upon completion.

Communicate clearly. Establish a single point of contact on both sides. Have regular check-in meetings to discuss progress and address concerns.

Plan for changes. Changes are almost inevitable in a renovation project. Decide in advance how you will handle change orders and who pays for them.

Managing the Renovation Timeline

A realistic timeline is essential for a successful renovation. Build in time for planning, permitting, ordering materials, and unexpected delays.

Planning and design (2 to 4 months). This includes assessing the building, setting goals, getting bids, and finalizing the design.

Permitting and approvals (1 to 3 months). The time required for permits varies widely by location. Start early.

Ordering equipment and materials (1 to 2 months). Some equipment has long lead times, especially if it needs to be custom-built.

Construction (1 to 3 months). The actual construction time depends on the scope of work and the size of the crew.

Commissioning and testing (1 to 2 weeks). After construction, test all systems before moving animals back in.

Repopulation (1 to 2 weeks). Moving animals back into the barn takes time and should be done carefully to minimize stress.

Plan your renovation around your farrowing and weaning schedule. The ideal time is when the barn is naturally empty or when you can shift animals to other facilities.

Monitoring and Recordkeeping After the Renovation

The renovation does not end when the construction crew leaves. You need to track results to confirm that you achieved your goals and to identify any problems that need correction.

Track production metrics. Compare preweaning mortality, weaning weights, average daily gain, and feed conversion before and after the renovation. Use the same measurement methods so the comparison is valid.

Monitor energy use. Track heating and cooling costs before and after the renovation. A successful renovation should reduce energy use per pig.

Track labor hours. Note how long it takes to clean and disinfect the barn between groups. A good renovation should reduce this time.

Document maintenance issues. Keep a log of any equipment failures or building problems that arise after the renovation. This will help you identify patterns and plan future maintenance.

Review the budget. Compare your actual expenses to your original budget. Note any areas where you underestimated costs. This information will improve your next budget.

Take photos. Photograph the completed renovation and keep the photos with your records. These are useful for insurance purposes and for planning future projects.

When to Call a Veterinarian or Extension Agent

You should involve professionals before, during, and after the renovation. Here are specific situations where their input is essential.

Call your veterinarian when:

  • You are changing the housing system for sows or piglets.
  • You are concerned about disease transmission during construction.
  • You need advice on biosecurity protocols for construction crews.
  • You are planning changes that affect animal flow or piglet care.
  • You see health problems after the renovation that you cannot explain.

Call your extension agent when:

  • You are deciding between renovation and new construction.
  • You need help estimating costs or comparing options.
  • You want recommendations for building design and equipment.
  • You need help interpreting production data after the renovation.
  • You are applying for grants or cost-share programs.

Call a structural engineer when:

  • You are making major changes to the building structure.
  • You are concerned about the condition of the foundation or roof.
  • You are adding equipment that will add significant weight to the structure.

Professional advice is a small cost compared to the total investment in a renovation. Use these resources early and often.

Environmental and Regulatory Considerations

Renovations can trigger environmental and regulatory requirements. Check with the appropriate agencies before you start.

Manure management. If your renovation changes the number of animals you can house, you may need to update your manure management plan. Check with your state environmental agency.

Water discharge. Changes to drainage and wastewater systems may require permits. An open lot or a new manure storage area may have different requirements than an existing system.

Building permits. Most renovations require a building permit. The requirements vary by location and by the scope of the work.

Zoning and land use. Check that your renovation complies with local zoning and land use regulations.

Worker safety. Ensure that the renovated facility complies with occupational safety requirements. This includes proper ventilation, lighting, and safe access to equipment.

Animal welfare. Some markets and buyers have specific animal welfare requirements. If you sell to a packer with welfare standards, make sure your renovation is compatible with those standards.

Tax Considerations

A barn renovation can have significant tax implications. Consult with a tax professional who understands agriculture.

Depreciation. Structural improvements to a building are typically depreciated over a longer period than equipment. Understand the difference and plan accordingly.

Section 179 deduction. Equipment purchases may qualify for the Section 179 deduction, which allows you to deduct the full cost in the year of purchase. Check the current limits and eligibility rules.

Repair versus improvement. The IRS distinguishes between repairs and improvements. Repairs are deductible in the current year, while improvements must be capitalized and depreciated. Make sure your contractor provides invoices that clearly describe the work.

Energy efficiency incentives. Some energy efficiency improvements may qualify for tax credits or deductions. Check with your tax professional.

Recordkeeping. Keep all receipts and invoices organized. Take photos of the work at each stage. This documentation is essential for tax purposes.

Case Studies in Renovation Planning

While every farm is different, these examples illustrate common scenarios and how producers might approach them.

Small farrow-to-finish operation. A producer with 100 sows wants to improve piglet survival and reduce labor. The barn is from the 1990s and has solid concrete floors, individual crates, and a basic ventilation system. The renovation focuses on replacing flooring with plastic-coated expanded metal, installing new crates with better piglet protection, and upgrading the ventilation controller. The total cost is estimated at 60 percent of the cost of a new barn. The producer finances the project with an operating loan and expects to pay it back within five years through reduced mortality and lower heating costs.

Large wean-to-finish operation. A producer with a 2,000-head nursery wants to expand to 2,500 head and improve air quality. The building is structurally sound but has inadequate ventilation and outdated pens. The renovation includes new ventilation fans and controllers, additional insulation, and reconfiguration of the pens to add capacity. The producer gets three bids and chooses a contractor with extensive experience in swine facilities. The project is completed in six weeks during the summer when the nursery is between groups.

Contract grower facing upgrade requirements. A contract grower is told by the integrator that the barn must meet new animal welfare standards or the contract will not be renewed. The required changes include more space per pig and environmental enrichment. The grower works with the integrator to understand the requirements and gets estimates for the work. The grower applies for a Farm Service Agency loan and completes the upgrades within the integrator's deadline.

Frequently Asked Questions

How much does a farrowing barn renovation cost per crate?

The cost varies widely depending on the condition of the building and the scope of work. A complete renovation that includes new flooring, crates, and ventilation can cost 3,000 to 6,000 dollars per crate. A more limited renovation that focuses on equipment replacement might cost 1,500 to 3,000 dollars per crate. Get detailed bids from contractors before setting your budget.

Should I renovate or build a new barn?

Build new if the structure has serious problems, the layout is incompatible with modern equipment, or the cost of renovation approaches 70 percent of the cost of new construction. Renovate if the building shell is sound and the layout can accommodate your goals. Create a spreadsheet comparing the total costs of both options, including lost production during construction.

How long does a barn renovation take?

A typical farrowing barn renovation takes 4 to 12 weeks, depending on the scope of work and the size of the crew. Nursery barn renovations are often faster, taking 3 to 8 weeks. Plan for the barn to be out of production during construction. Build extra time into your schedule for unexpected delays.

Can I renovate while the barn is in use?

It is possible but not recommended. Construction creates dust, noise, and stress for animals. It also increases the risk of disease introduction. If you must keep animals in the barn, isolate the construction area and take extra biosecurity precautions.

What are the most important improvements for piglet survival?

Flooring, ventilation, and crate design are the most important factors. Good flooring prevents injuries and keeps piglets clean and dry. Proper ventilation prevents chilling and respiratory disease. Crate design protects piglets from being crushed by the sow.

How do I pay for a renovation?

Options include operating loans, equipment loans, real estate loans, Farm Service Agency loans, and leasing. Some states offer grants or cost-share programs. Prepare a business plan that shows how the renovation will improve your bottom line before approaching a lender.

What permits do I need for a barn renovation?

Requirements vary by location. You will likely need a building permit. You may also need environmental permits if the renovation affects manure management or drainage. Check with your local planning office and state environmental agency early in the process.

How do I choose a contractor?

Ask for recommendations from other producers, your veterinarian, and your extension agent. Check that the contractor is licensed and insured. Ask for references and call them. Get at least three bids on the same written scope of work. Choose based on quality, experience, and price, not price alone.

Related Farming Guides

This section will be populated with links to related farming guides on farrowing barn design, nursery management, swine ventilation systems, biosecurity planning, and capital budgeting for livestock facilities. Check back for updates.

Related Clinical & Scientific Guides

References

  • National Pork Board: https://www.pork.org/
  • USDA APHIS Swine Health: https://www.aphis.usda.gov/livestock-poultry-disease/swine
  • FAO Pig Production: https://www.fao.org/pig-production-and-products/en/
  • FAO Animal Production and Health: https://www.fao.org/animal-production/en/
  • WOAH (World Organisation for Animal Health): https://www.woah.org/en/home/

This article is educational and is not a substitute for veterinary diagnosis, treatment, public-health guidance, or regulatory reporting.